Decision map: what to open, and when
Each cell is one combination of the two regions' demand at the chosen year (further right: more demand in region A; further up: more in region B). Its colour is the optimal move from the network you would have then; faint cells are unlikely to be reached.
Distribution of NPV
The best fixed network against the best flexible strategy, over the same simulated demand paths.
Pooling and correlation
Each strategy's NPV as the correlation between the regions changes (everything else as set). The dashed line is your setting.
Table view
The model
Two regions, money in $M. The equations run in src/network.js, which is checked by
its own automated tests, including an exact reduction to the single-site engine when one region is empty.
Joint demand lattice
Four branches per quarter. Each region's growth is reproduced exactly and the moves have correlation ρ; if a growth or a correlation cannot be represented, the page says what is used instead.
Serving the network
Cross-region service earns the margin less the transport cost x, and is used before the 3PL when it earns more.
Compound option
With one hub open, the option to open the other; with none, the choice of which to open first, or both. Each project arrives after the build lead time; during it no other project starts.
Fixed designs
The best fixed network is the better of a central hub and two regional hubs, each optimally sized; the value of flexibility is measured against it.